Old Salisbury Road Infrastructure Improvements

Project Update

December 2022: The project’s design is ongoing with the next plan development submittal anticipated in Winter of 2023. The road currently remains closed to traffic.

 

October 2022: Preliminary design plans have been reviewed and approved. 

 

March 2022: Contract for design services authorized by City Council.

 

November 2022: Awarded design services to qualified consultant.

 

About the Project

The City of Winston-Salem has determined it necessary to repair a segment of Old Salisbury Road between Brewer Road and Gyro Drive. An embankment failure occurred along Old Salisbury Road in Spring of 2021 causing a portion of the travel lane to crack significantly. This project will repair roadway and shoulders, stabilize embankment slopes, replace drainage pipes and a concrete box culvert structure. The project will also install guardrail for safety and repair other affected public infrastructure such as utilities.

Project Details

Project Type:              Roadway and Drainage Improvement Project

Project Budget:           $2,900,000

Design Engineer:        KCI Associates of North Carolina, P.A.

Contractor:                  To Be Determined

 

Schedule

 

Date 

Activity

Spring 2022

Project Design started

Spring/Summer 2023

Project Design Complete

To Be Determined

Construction Start

To Be Determined

Construction Completed

 